Company
LINAK is a privately-owned Danish manufacturing company specialized in linear actuators. The CEO and owner, Bent Jensen, took over from his father in 1976; since then the company has expanded from seven employees to more than 2000 in 35 countries.
Given the history of the company, there is a strong culture and great pride in the success that the employees create, and with an important presence and significant production in the small town of Guderup in Southern Jutland, the company represents the best of Danish manufacturing.
LINAK is divided into four divisions, one of which is DESKLINE. DESKLINE specializes in actuators for ergonomic desks. In response to rapidly expanding sales, short supply of labor and limits to the footprint of the factory, the DESKLINE division has initiated a drive toward production automation wherever feasible. The factory processes have been optimized by introducing LEAN principles, and the production cells are operated in three shifts during peak periods.
The pilot project
The pilot project was initiated in response to the learnings from the first five automation projects where the capacity was added in addition to the current semi-automated production cells by adding fully automated cells based on robots. These projects were regarded a success in terms of reaching the production targets and quality required, but the duration of the projects was too long, and the costs rose from project to project due to increased complexity and higher requirements from LINAK.
The scope of the project was defined as the specification, design, sourcing, installation and commissioning of a robot-based automated production cell that can triple the current production capacity. The project was initiated by the head of the DESKLINE division, and the DESKLINE Operation Manager was appointed Project Owner. The project manager was chosen based on the criteria that he had run automation projects before and that he had experience working with the supplier for the project in question.
The supplier had supplied most of recent automation projects, and a key element to work with in the project was the customer/supplier relationship, which was rated as good but not necessarily efficient.
Project results
- Target: Execution time of maximum 9 months (38 weeks) from project start (the kick-off with a supplier) to finish (Site acceptance test at LINAK’s factory)
Results: Reduced from an original plan of 60 to 39 weeks – delivered in 40 weeks. - Target: 25% cost reduction on hours from supplier compared to a similar on-going project
Results: Current expectation is a saving less than 20%, but it is unclear how much is related to reuse of designs from other projects and reuse of control software, and how much is related to the elimination of a factory acceptance test. There is an ongoing discussion about the baseline that the project should be compared up against - Target: LINAK’s LEAN office capable of replicating the approach on other projects after completion of the pilot
Results: Challenged due to change of staff in the LEAN office. Management contracts introduced to drive leadership behaviour on new projects. - Target: The supplier adopts the methodology and is willing to execute projects the same way again
Results: Above expectations, as the supplier is rolling out visual plans across the whole project organization and is convincing their other customers to adopt a similar methodology.
Local implementation
The three core elements of the Half Double Methodology, Impact, Flow and Leadership, were specifically tailored to fit the LINAK project as well as the supplier of the automated production cell.
Impact case and follow up on KPI’s to ensure impact: The two main drivers in the impact case was;
- i) the quicker the production switch from manual to automated production, the quicker LINAK can benefit from the significant lower unit cost, and
- ii) efficiency improvement on the supplier side would reduce the cost of the project runs.
LINAK uses a standard financial model to evaluate investments in automation and other production improvements. This model uses payback time from project completion as the main decision criterion. It does not take into account the accumulated benefits during the project period and the earlier go-live date. The importance of this limitation of the model became clear when the CEO was asked to approve the preliminary impact case earlier in the project thereby accepting additional risk. The benefit of this early approval was an earlier project completion date, but this could not be reflected in the financial model used for the impact case. In the project, this challenge was solved in an elaborated dialogue between the CEO and the project owner.
In the initial workshops, a shared cost/benefit model for the project was briefly discussed but was not pursued further.
Impact solution design in the initiation of the project: The impact solution design for the project was developed through the first three workshops between LINAK and the supplier: the project initiation workshop, the project planning workshop, and the project kick-off. The ideas came from a mix of retrospective views on previous projects and from challenging the current project model using a series of what-if questions.
The core idea was to take a different view on project risk to accept more risks related to speed but accepting that the total cost of the project would not be fixed. Several important principles in the current project model were therefore adjusted accordingly.
- Immediately after kick-off, the project sponsor secured the go-ahead from LINAK’s CEO for the supplier to start detailed design of the solution based on a preliminary business case and the supplier’s non-binding calculation of project costs. The supplier was to be compensated on a cost and material basis. In a standard project, the design will not be initiated before a fixed priced contract for the entire project has been agreed.
- The supplier agreed to order three standard robots with a long lead time, thus taking the risk of having to put them in inventory if the project was canceled.
- LINAK’s CEO also approved the early investment in certain critical and expensive components with a long lead time in order to cut waiting time during assembly.
- The factory acceptance test at the supplier’s factory was skipped to reduce cost and save time, with final assembly done directly on LINAK’s factory floor. The risk is that the commissioning will take significantly longer and be more expensive as the specialists from the suppliers are based a three-hour drive from LINAK.
In addition to the changed view on project risks, several other initiatives were taken to reduce time and at every weekly solution feedback meeting, new optimizations were explored.
Allocation of core team
The core team consists of LINAK’s project manager, the supplier’s project manager, the lead engineers from the supplier, and key technicians. Allocation for all team members is high, with the caveat that there are periods where not all have tasks to solve. One example is the head of assembly at the supplier who will be 100% allocated for a specific period, but has almost no tasks in the early and late phases of the project. From the beginning, the core team consisted of four people from the supplier and LINAK’s project manager.
Fixed project heartbeat for stakeholder interaction
Due to project participants’ allocation changing over time, at each new sprint it is evaluated who should be part of each of the interactions, i.e. solution feedback or daily standup. There are more participants than both LINAK and the supplier would normally select, as frequent interaction and feedback are the key to progress faster than normal on the project. Six key events were defined requiring only minor adaptions to the general Half Double Methodology. The biggest difference from other Half Double projects is probably the significant presence of senior members from the supplier in key events.
Pulse Checks
Pulse checks are carried out every two weeks including the same participants as in the sprint planning sessions with a maximum of nine respondents. The frequency was selected to fit the project heartbeat and the results are discussed at the four-weekly sprint review sessions and at one of the ‘plan next week session’ in between. This turned out to be a good frequency as the team can address issues and take corrective measures before challenges arise.
Visual tools and plans
In the project team, the supplier is responsible for producing the deliverables, while LINAK is responsible for making decisions and creating the design specification. However, the two companies are located a three-hour drive away from each other and therefore have to take travel time into account when selecting and designing tools. Initially, the sprint plan was created on a physical poster with the entire team being present.
However, it soon turned out that active participation in the daily and weekly Skype sprint meetings were difficult for the LINAK team members. The team began to use a tool called Virtual Visual Planner (VVP) which is a digital version of a sprint planning board. This tool worked extremely well because it maintained the sprint structure and allowed all team members to modify post-its in real time while conduction the meeting using Skype. The tool is intuitive and requires no training to be used effectively – and can therefore be integrated into the project effortlessly. The tool supported the active participation of all team members as they are all able to add and modify their own post-its in real time. In the assembly phase, plans will be posterbased as the technicians have to have access without opening a computer.
Collaborative project leadership
LINAK’s project manager has engaged deeply with the supplier’s project organization and spent much work time at the supplier’s site. The resulting understanding of the challenges faced by the supplier opens for a trustful customer/supplier relationship where the focus is on moving the project forward and challenge design decisions where appropriate. Furthermore, this approach bridges the “them” and “us” mentality that can develop in a project of this kind.
Active, committed and engaged project owner
LINAK’s project owner prioritizes the fixed events and is constantly driving towards the maximum impact. The project owner was chosen as he would be responsible for production afterwards and can make critical decisions fast related to the design and scope as well as judging risks. This power was put to good use in the project with key decisions taken directly at the workshops or right after.
The project financing and overall go/no-go decision was made at CEO level; the project owner was not mandated to change the financial evaluation model. The key challenge in the project is the objective of reducing project cost by a more efficient production at the supplier. As the project owner does not have a direct mandate, a close and trustful dialogue between the project owner and the leaders of the supplier’s project organization is required. And maybe a different contract paradigm.
Local translation and adaption to governance
The main elements of local translation are related to the fact that two companies are involved with a clear customer/supplier relationship but also a very clear agenda focusing on the mutual success. There are many similar projects in the pipeline and fast, efficient execution with maximum impact is essential for LINAK to meet market demands at a competitive price. The common understanding of this was established and has enabled the project to meet deadlines and targets so far.
The project is a LINAK project, but as the supplier has more participants than LINAK in most key events, the project has had a significant impact at the supplier. However, the supplier has a production planning system where cost optimization is in focus. In certain cases, this affects lead time in production; in order for the Half Double project to progress optimally, the supplier would have had to change their production planning system. However, introducing a new production planning method or system in the middle of this pilot project was judged too risky, and was likely to lead to a longer overall lead time the first time.
A couple of stories from the pilot project at LINAK
Factory acceptance test – a story about quality, cost and staff travelling. Early on, it became clear that skipping the factory acceptance test (FAT) and pilot production at the supplier could significantly reduce project duration and potentially save costs if commissioning was smooth. However, this meant that the supplier’s key staff would have to spend more time at LINAK away from home and the cost of man hours would rise with travel and accommodation costs. The leadership teams at LINAK and the supplier agreed to find a solution to this with a shared risk approach, as cost for travelling and accommodation for LINAK’s employees would be reduced.
Visit to sub-suppliers – don’t accept standard lead time. It became clear that the lead time on a certain made-to-measure component was on the critical path and that this blocked a lot of other initiatives to reduce the total duration of the project. Instead of just pushing the supplier, the project owner visited the sub-supplier and discussed scheduling. This active approached resulted in a significant reduction in lead time and opened for other optimization.
We have a variety of Half Double Video's available on Youtube and Vimeo.
Read more about the results of the pilot project at Linak in this report from Aarhus University.